Introduction

Project description
Demolition of existing residence and building replacement dwelling.
Ecologist’s name and contact details
Turnstone Ecology
Planning authority
Peak District National Park
Brief site description
Detached dwelling adjacent woodland.

Pre-works roost structure

Type of structure
Building
Use
Domestic Dwelling
Condition
Not In Use
Main construction material of walls
Brick
Roof design
Hipped
Roof material
Clay Tiled
Internal roof structure
Timber Frame
Lighting present on site and its proximity to the roost
Not reported
Photos or annotated figures of roost structure

Pre-works roost description

Species
Brandt’s bat
Number of bats max count
12
Type of roost
Maternity Roost
Evidence of bats
Bats Recorded Emerging/Re-entering
Roost location
Under Roof Tiles
Aspect of roost
W
Height of roost entrance (m)
4.5
Roost material(s)
  • Bitumen Felt
  • Clay Hanging Tiles
Nearest commuting feature
Woodland
Distance to nearest commuting feature (m)
Not reported
Photos or annotated figures of roost

Proposed works

Description of works
Demolition of existing residence and building replacement dwelling.
Type of impact upon the roost
Long-Term Roost Modification and Roost Loss
Relevant annotated figures

Proposed mitigations

Type of mitigation
Compensation
Specific technical detail of measure
Bat House: Objective was to move the maternity colony of Brandt's bats and day roost of Common Pipistrelles to a purpose built bat barn in a separate area of the clients land so that populations of bats could continue to use the site and so that the local and regional populations of bats were not adversely affected.

The replacement barn was constructed over winter 2012/13 and was built using as much material from the old roost as was possible without destroying the roost. This involved using wooden weatherboarding from the front of the original house, and removing the insulation from the original house and filling the new barn. The replacement barn was designed to replicate the locations bats were observed using, including; ridge tile access, raised tiles along the hipped end of the barn, lifted lead access tiles and internal beams. The aspects of each face of the barn were positioned so that the solar regime the new building was subjected to would replicate that of the original structure. Once the barn was completed and the weather was suitable the roof and ridge tiles were stripped by hand and the bitumastic lining was also removed (all tile stripping was completed by our intrepid licence holder Simon Parker who was roped to the roof).

Size: The overall dimensions of the building are 5 m x 7.5 m with a ridge height of approximately 4.25 m. The internal ridge height of the bat loft area is 2 m.

Materials: Oak main frame, softwood pressure treated internal trusses, a mixture of new and reclaimed concrete roof tiles, bitumastic lining, reclaimed wooden weatherboards from original house, lead flashing and plyboard flooring.

Additional info: The planned location for the replacement bat barn contained several small trees and was adjacent to an outgrown laid hedgerow. The small trees were removed or coppiced and the hedgerow was re-laid so that the amount of sunlight hitting the new barn was as high as possible.
Relevant annotated figures
Roost location
Under Roof Tiles
Aspect of roost
S
Height of roost entrance (m)
4.25
Roost material(s)
  • Bitumen Felt
  • Clay Hanging Tiles
Nearest commuting feature
Hedge
Distance to nearest commuting feature (m)
Not reported
Internal temperature and humidity of roost
29.5
External temperature and humidity of roost
22.5
Photos or annotated figures of roost

Actual mitigations implemented

Type of mitigation
Compensation
Specific technical detail of measure
Bat House: Objective was to move the maternity colony of Brandt's bats and day roost of Common Pipistrelles to a purpose built bat barn in a separate area of the clients land so that populations of bats could continue to use the site and so that the local and regional populations of bats were not adversely affected.

The replacement barn was constructed over winter 2012/13 and was built using as much material from the old roost as was possible without destroying the roost. This involved using wooden weatherboarding from the front of the original house, and removing the insulation from the original house and filling the new barn. The replacement barn was designed to replicate the locations bats were observed using, including; ridge tile access, raised tiles along the hipped end of the barn, lifted lead access tiles and internal beams. The aspects of each face of the barn were positioned so that the solar regime the new building was subjected to would replicate that of the original structure. Once the barn was completed and the weather was suitable the roof and ridge tiles were stripped by hand and the bitumastic lining was also removed (all tile stripping was completed by our intrepid licence holder Simon Parker who was roped to the roof).

Size: The overall dimensions of the building are 5 m x 7.5 m with a ridge height of approximately 4.25 m. The internal ridge height of the bat loft area is 2 m.

Materials: Oak main frame, softwood pressure treated internal trusses, a mixture of new and reclaimed concrete roof tiles, bitumastic lining, reclaimed wooden weatherboards from original house, lead flashing and plyboard flooring.

Additional info: The planned location for the replacement bat barn contained several small trees and was adjacent to an outgrown laid hedgerow. The small trees were removed or coppiced and the hedgerow was re-laid so that the amount of sunlight hitting the new barn was as high as possible.
Relevant annotated figures
Roost location
Under Roof Tiles
Aspect of roost
S
Height of roost entrance (m)
4.25
Roost material(s)
  • Bitumen Felt
  • Clay Hanging Tiles
Nearest commuting feature
Hedge
Distance to nearest commuting feature (m)
Not reported
Internal temperature and humidity of roost
29.5
External temperature and humidity of roost
22.5
Photos or annotated figures of roost

Monitoring data

Length of monitoring proposed
Not reported
Frequency of monitoring
Not reported
Type of monitoring
Dusk and Dawn Survey
Date and time
1st July 2013
Evidence recorded
The internal walkway and beams were swept clear of bat droppings following the installation of the old insulation to allow easier identification of fresh bat droppings. Common Pipistrelle droppings were found scattered over this and a small collection of Brandt's droppings were found in one location. An emergence survey was completed in July 2013, during this at least two Brandt's bats emerged from the new bat barn (one from the south west hipped end and one from the west side of the ridge) along with an individual Common Pipistrelle which emerged from the western face of the roof.

Pipistrelle droppings were found within 4 weeks of completion of the bat barn (April 2013), Brandt's bat droppings were found on our monitoring visit which was completed in July (4 months).
Interventions made
Possibly add more insulation at a later date, and if temperatures are not shown to be staying high enough heating will be added in an attempt to encourage bats to breed on site once again.

Final details

Lessons learned
Little is known about Brandt's bats and their requirements with regards to mitigation and roost specification. This project has given an indication that replicating as many features as possible between the original roost and the replacement roost is important. This along with another project involving Brandt's roosts we have had over the last year has led to the suggestion that this species of bat is sensitive to temperature changes within a roost. Both the roosts were inhabited by people until approximately two years ago, and the evidence we found within would suggest that the roosts were previously much much larger (Oak House contained huge numbers of droppings under the ridge tiles, below lifted tiles and within the loft space - many more than the numbers of bats we found during surveys could produce even over a long time period) We were very lucky to have a willing client, an experienced architect and an excellent builder, all of whom listened to our instructions and implemented them as required.